In capacity as: CIVIL CONSTRUCTION PROJECT MANAGER Knife River Corporation – Minot, North Dakota (Purchased Strata Corp. Feb 2025)
Water Main and Services Replacement (2024-2025) Minot, North Dakota University Avenue Water Main Replacement for City of Minot. Replaced 5500’ water main
Replacement of curb stop and boxes
Reconnection of existing services to water main for 90 residents
Drainage Improvement (2024) Sidney, Montana Anderson Subdivision Storm Sewer and custom inlet structures for city of Sidney.
700’ new storm sewer
Coordinated custom manufacture of unusual, specific specs on two inlet structures
Located suppliers overseas to acquire the most cost-effective materials
Organized sub-contractors and manufacturers to receive materials and install in proper sequence
Poured foundation for a prefabricated aluminum building
Coordinated manufacturer install team to set the building
Storm Sewer and New Street (2024) Watford City, North Dakota Street construction at 3rd Ave SW for Watford City.
1500’ new storm sewer
Replaces existing gravel road with new residential street
New curb, gutter, and sidewalk
Culvert Rehabilitation (2023) Minot, North Dakota Sirroco Drive Culvert Rehabilitation for Minot Air Force Base.
Rectified concrete deterioration
During rehab, I noticed one of the incoming storm drains was infiltrating dirt and submitted proposal to repair incoming drain, outside of contract, for improved final product
Street Overhaul and Apron (2023) Minot, North Dakota Street Overhaul for the North Dakota National Guard Base.
Removed asphalt on 250’ street with poor soil and drainage issues and replace with concrete
Removed 10’ of apron
Placed void form under Earth aggregate layer to prevent future movement from saturated clay
Proposed laying geogrid instead of fabric due to ground conditions
Northeast Tioga Reconstruction Phase 2 (2023) Tioga, North Dakota Replaced water main and sanitary sewer, placed asphalt and necessary concrete to complete road for the city of Tioga.
Assumed this project in 2023 upon employment with Strata Corp; previously drew up plans with Moore Engineering in 2020
Replaced 4000’ Water Main
Replaced 4000’ Sanitary Sewer
Poured new curb and gutter, sidewalks, and asphalt
Coordinated with sub-contractors and suppliers for required materials
Interacted professionally and appropriately with uncooperative owners
In capacity as: CIVIL ENGINEERING TECH III and CAD TECH III Moore Engineering, Inc. - Minot, North Dakota
Water Treatment Plant Addition (2023) Garrison, North Dakota Rerouting of existing transmission lines for raw water municipality and rural water for the City of Garrison.
Management of 12-man crews
Concrete/rebar installation for new foundation
Sanitary Sewer Reline (2023) Makoti, North Dakota Cleaning, televising, and relining of 6,000+ linear feet of sanitary sewer for the City of Makoti.
Water Tower Project (2023) McClusky, North Dakota Erection of steel water tower with concrete foundation for the City of McClusky.
Ensure foundation rebar and concrete poured per specification
Worked closely with weld and coating inspectors
Coordinated with cities and coating installers to ensure finishing art was correct
North Dakota DOT Road (2022) Minot, North Dakota Road work to improve road smoothness for vehicle traffic within 10 city blocks for the City of Minot.
Management of all equipment and 15-man crews: dirt, concrete, asphalt, electrical, seeding, traffic control, and stripers
Mill and overlay, and surface restoration
ADA improvements and successful traffic control
Ensured job site safety
Northeast Tioga Reconstruction Sout Main Street Project (2021) Northeast Tioga Reconstruction Phase 1 (2020) Tioga, North Dakota Resident Project Representative for $5 million sanitary sewer, storm sewer, water main and street improvements for the City of Tioga.
9 blocks sanitary sewer
2 blocks storm sewer
10 blocks water main replacement
Water Tower Project (2020) Glenburn, North Dakota Erection of steel water tower with concrete foundation for the City of Glenburn.
Ensure foundation rebar and concrete poured per specifications
Worked closely with weld and coating inspectors
Coordinated with cities and coating installers to ensure finishing art was correct
Water Main Replacement (2019) McClusky, North Dakota Water main, storm sewer and service replacement for the City of McClusky.
12 blocks water main replacement
Lead services removed and replaced
2 blocks storm sewer and related ditching
Water Tower Project (2019) Turtle Lake, North Dakota Erection of steel water tower with concrete foundation for the city of Turtle Lake.
Ensure foundation rebar and concrete poured per specifications
Worked closely with weld and coating inspectors
Coordinated with cities and coating installers to ensure finishing art was correct
Water Tower Project (2019) Makoti, North Dakota Erection of steel water tower with concrete foundation for the City of Makoti.
Ensure foundation rebar and concrete poured per specifications
Worked closely with weld and coating inspectors
Coordinated with cities and coating installers to ensure finishing art was correct
Pouring of curb, gutter and asphalt for large parking lot and access road
Sewer, Water and Storm Sewer Improvements (2018) Glen Ullin, North Dakota Resident Project Representative for $5 million USDA Rural Development funded sanitary sewer, storm sewer and water main replacement project for the City of Glen Ullin.
Spot repairs and relining of sanitary sewer for entire city
4 blocks storm sewer improvements
7 blocks water main replacement
Sanitary Sewer and Water Main Replacement (2017) Rolette, North Dakota Resident Project Representative for $2.1 million USDA Rural Development funded sanitary sewer and water main replacement project for the City of Rolette.
9 blocks of sanitary sewer
7 blocks water main replacement
Water Treatment Plant Improvements (2017) Rolla, North Dakota Resident Project Representative for $3.88 million USDA Rural Development funded water system improvement project for the City of Rolla.
Installation of new water production wells
Installation of raw water transmission line to the water treatment plant
Storm Sewer Improvements (2016) Harvey, North Dakota Resident Project Representative for a storm sewer installation project for the City of Harvey.
Installation of 4-blocks of 48-inch storm
Installation of 3 blocks of 12-inch storm sewer
Street Rehab and Drainage (2016) Fessenden, North Dakota Resident Project Representative for Bank of ND’s Infrastructure Revolving Loan Fund funded storm sewer replacement project for the City of Fessenden.
Surface and subsurface drainage improvements within the community
Stonebridge 3rd Addition (2015) Minot, North Dakota Resident Project Representative of privately constructed Stonebridge subdivision for the City of Minot.
Installation of curb and gutter
Street improvements
Street Rehabilitation and Storm Sewer Placement (2014) Rolla, North Dakota Resident Project Representative for a utility and street replacement project for the City of Rolla.
7 blocks of storm sewer replacement
Street rehab
Asphalt placement
Street Rehabilitation (2013) Hazen, North Dakota Resident Project Representative for street reconstruction and rehabilitation project for the City of Hazen.
Asphalt milling
HBP asphalt overlay
Sanitary Sewer Design (2012) Benedict, North Dakota Drafting and preparation of plans for three blocks of sanitary sewer replacement for the City of Benedict.
Site Design and Observation of Minot Infrastructure Improvements (2012) Minot, North Dakota Infrastructure design and observation for the City of Minot.
Designed and observed tie-ins and connections for privately owned/constructed projects within the city
Observed and documented construction of city infrastructure improvements
In capacity as: CONSTRUCTION, CONCRETE FOUNDATION CREW FOREMAN Blankenship Quality Concrete - Cody, WY
Buffalo Bill Historical Center Addition Cody, Wyoming Mechanical Room addition to the BBHC complex using 240 linear feet of 40-foot tall, 16” thick walls.
Draper Natural History Museum Addition Cody, Wyoming Addition to the Buffalo Bill Historical Center complex using 210 linear feet of 40-foot tall, 16” thick walls, of which 100’ was poured on a 100’radius.
Shoshone Irrigation District Improvements Park County, Wyoming Concrete inlet, outlet and overflow structures for 4’ inverted syphon, for 300 linear feet. View InletView OutletView Overflow.
Shoshone Irrigation District Improvements Park County, Wyoming Replacement of irrigation diversion dam with fish ladder on north side of Greybull River, placement of gates, imbeds and riprap.
Private Home Cody, Wyoming Erection of multi-dimensional, new home foundation with various wall height and thicknesses. Implemented hollow core flooring for first floor.