Adam "Scott" Myers

Civil Construction Project Manager
​
​
​Civil Engineering Specialist

Management projects


In capacity as:
CIVIL CONSTRUCTION PROJECT MANAGER
Knife River Corporation – Minot, North Dakota (Purchased Strata Corp. Feb 2025)
 
Water Main and Services Replacement (2024-2025)
Minot, North Dakota
University Avenue Water Main Replacement for City of Minot.
Replaced 5500’ water main
  • Replacement of curb stop and boxes
  • Reconnection of existing services to water main for 90 residents
 
Drainage Improvement (2024)
Sidney, Montana
Anderson Subdivision Storm Sewer and custom inlet structures for city of Sidney.
  • 700’ new storm sewer
  • Coordinated custom manufacture of unusual, specific specs on two inlet structures
 
Sanitary Sewer and Water Replacement (2024)
Minot, North Dakota
Beacon Street Sanitary Sewer and Water Main Replacement for City of Minot.
  • Replaced 800’ of Sanitary Sewer
  • Replaced 700’ of Water Main
  • Steadfast communication with owner due to many issues; on-site often and on call 24/7
  • Navigated excessive failures with faulty existing infrastructure and incorrect owner information
  • Successfully addressed resident concerns and resolved unreasonable number of employee issues
 
Surge Tank and Prefab Building Installation (2024)
Ray, North Dakota
City of Ray Surge Tank and Utility Building.
  • Located suppliers overseas to acquire the most cost-effective materials
  • Organized sub-contractors and manufacturers to receive materials and install in proper sequence
  • Poured foundation for a prefabricated aluminum building
  • Coordinated manufacturer install team to set the building
 
Storm Sewer and New Street (2024)
Watford City, North Dakota
Street construction at 3rd Ave SW for Watford City.
  • 1500’ new storm sewer
  • Replaces existing gravel road with new residential street
  • New curb, gutter, and sidewalk
 
Culvert Rehabilitation (2023)
Minot, North Dakota
Sirroco Drive Culvert Rehabilitation for Minot Air Force Base.
  • Rectified concrete deterioration
  • During rehab, I noticed one of the incoming storm drains was infiltrating dirt and submitted proposal to repair incoming drain, outside of contract, for improved final product
 
Street Overhaul and Apron (2023)
Minot, North Dakota
Street Overhaul for the North Dakota National Guard Base.
  • Removed asphalt on 250’ street with poor soil and drainage issues and replace with concrete
  • Removed 10’ of apron
  • Placed void form under Earth aggregate layer to prevent future movement from saturated clay
  • Proposed laying geogrid instead of fabric due to ground conditions
 
Northeast Tioga Reconstruction Phase 2 (2023)
Tioga, North Dakota
Replaced water main and sanitary sewer, placed asphalt and necessary concrete to complete road for the city of Tioga.
  • Assumed this project in 2023 upon employment with Strata Corp; previously drew up plans with Moore Engineering in 2020
  • Replaced 4000’ Water Main
  • Replaced 4000’ Sanitary Sewer
  • Poured new curb and gutter, sidewalks, and asphalt
  • Coordinated with sub-contractors and suppliers for required materials
Interacted professionally and appropriately with uncooperative owners

In capacity as:
CIVIL ENGINEERING TECH III and CAD TECH III
Moore Engineering, Inc. - Minot, North Dakota                                                    

Water Treatment Plant Addition (2023)
Garrison, North Dakota
Rerouting of existing transmission lines for raw water municipality and rural water for the City of Garrison.
  • Management of 12-man crews
  • Concrete/rebar installation for new foundation
 
Sanitary Sewer Reline (2023)
Makoti, North Dakota
Cleaning, televising, and relining of 6,000+ linear feet of sanitary sewer for the City of Makoti.
 
Water Tower Project (2023)
McClusky, North Dakota
Erection of steel water tower with concrete foundation for the City of McClusky.
  • Ensure foundation rebar and concrete poured per specification
  • Worked closely with weld and coating inspectors
  • Coordinated with cities and coating installers to ensure finishing art was correct
 
North Dakota DOT Road (2022)
Minot, North Dakota
Road work to improve road smoothness for vehicle traffic within 10 city blocks for the City of Minot.
  • Management of all equipment and 15-man crews: dirt, concrete, asphalt, electrical, seeding, traffic control, and stripers
  • Mill and overlay, and surface restoration
  • ADA improvements and successful traffic control
  • Ensured job site safety
 
Northeast Tioga Reconstruction Sout Main Street Project (2021)
Northeast Tioga Reconstruction Phase 1 (2020)
Tioga, North Dakota
Resident Project Representative for $5 million sanitary sewer, storm sewer, water main and street improvements for the City of Tioga.
  • 9 blocks sanitary sewer
  • 2 blocks storm sewer
  • 10 blocks water main replacement
 
Water Tower Project (2020)
Glenburn, North Dakota
Erection of steel water tower with concrete foundation for the City of Glenburn.
  • Ensure foundation rebar and concrete poured per specifications
  • Worked closely with weld and coating inspectors
  • Coordinated with cities and coating installers to ensure finishing art was correct
 
Water Main Replacement (2019)
McClusky, North Dakota
Water main, storm sewer and service replacement for the City of McClusky.

  • 12 blocks water main replacement
  • Lead services removed and replaced
  • 2 blocks storm sewer and related ditching
 
Water Tower Project (2019)
Turtle Lake, North Dakota
Erection of steel water tower with concrete foundation for the city of Turtle Lake.
  • Ensure foundation rebar and concrete poured per specifications
  • Worked closely with weld and coating inspectors
  • Coordinated with cities and coating installers to ensure finishing art was correct
 
Water Tower Project (2019)
Makoti, North Dakota
Erection of steel water tower with concrete foundation for the City of Makoti.
  • Ensure foundation rebar and concrete poured per specifications
  • Worked closely with weld and coating inspectors
  • Coordinated with cities and coating installers to ensure finishing art was correct
 
Parking Lot, Storm Sewer, Utilities for Community Center (2019)
St. Cloud, Minnesota
Project management for Fond du Lac Reservation.
Staking out of gas, electric and communications locations for new installations
  • Pouring of curb, gutter and asphalt for large parking lot and access road
 
Sewer, Water and Storm Sewer Improvements (2018)
Glen Ullin, North Dakota
Resident Project Representative for $5 million USDA Rural Development funded sanitary sewer, storm sewer and water main replacement project for the City of Glen Ullin.
  • Spot repairs and relining of sanitary sewer for entire city
  • 4 blocks storm sewer improvements
  • 7 blocks water main replacement
 
Sanitary Sewer and Water Main Replacement (2017)
Rolette, North Dakota
Resident Project Representative for $2.1 million USDA Rural Development funded sanitary sewer and water main replacement project for the City of Rolette.
  • 9 blocks of sanitary sewer
  • 7 blocks water main replacement
 
Water Treatment Plant Improvements (2017)
Rolla, North Dakota
Resident Project Representative for $3.88 million USDA Rural Development funded water system improvement project for the City of Rolla.
  • Installation of new water production wells
  • Installation of raw water transmission line to the water treatment plant
 
Storm Sewer Improvements (2016)
Harvey, North Dakota
Resident Project Representative for a storm sewer installation project for the City of Harvey.
  • Installation of 4-blocks of 48-inch storm
  • Installation of 3 blocks of 12-inch storm sewer
 
Street Rehab and Drainage (2016)
Fessenden, North Dakota
Resident Project Representative for Bank of ND’s Infrastructure Revolving Loan Fund funded storm sewer replacement project for the City of Fessenden.
  • Surface and subsurface drainage improvements within the community
 
Stonebridge 3rd Addition (2015)
Minot, North Dakota
Resident Project Representative of privately constructed Stonebridge subdivision for the City of Minot.
  • Installation of curb and gutter
  • Street improvements
 
Street Rehabilitation and Storm Sewer Placement (2014)
Rolla, North Dakota
Resident Project Representative for a utility and street replacement project for the City of Rolla.
  • 7 blocks of storm sewer replacement
  • Street rehab
  • Asphalt placement
 
Street Rehabilitation (2013)
Hazen, North Dakota
Resident Project Representative for street reconstruction and rehabilitation project for the City of Hazen.
  • Asphalt milling
  • HBP asphalt overlay
 
Sanitary Sewer Design (2012)
Benedict, North Dakota
Drafting and preparation of plans for three blocks of sanitary sewer replacement for the City of Benedict.
 
Site Design and Observation of Minot Infrastructure Improvements (2012)
Minot, North Dakota
Infrastructure design and observation for the City of Minot.
  • Designed and observed tie-ins and connections for privately owned/constructed projects within the city
  • Observed and documented construction of city infrastructure improvements
 
In capacity as:
CONSTRUCTION, ​CONCRETE FOUNDATION CREW FOREMAN
Blankenship Quality Concrete - Cody, WY

Buffalo Bill Historical Center Addition
Cody, Wyoming
Mechanical Room addition to the BBHC complex using 240 linear feet of 40-foot tall, 16” thick walls.
 
Draper Natural History Museum Addition
Cody, Wyoming
Addition to the Buffalo Bill Historical Center complex using 210 linear feet of 40-foot tall, 16” thick walls, of which 100’ was poured on a 100’radius.
 
Buffalo Bill Historical Center Parking Lot
Cody, Wyoming
Poured and finished 85,000+ sq. ft. parking lot in 4 days with crew.
 
Shoshone Irrigation District Improvements
Park County, Wyoming
Concrete inlet, outlet and overflow structures for 4’ inverted syphon, for 300 linear feet.
View Inlet    View Outlet    View Overflow.
 
Shoshone Irrigation District Improvements
Park County, Wyoming
Replacement of irrigation diversion dam with fish ladder on north side of Greybull River, placement of gates, imbeds and riprap.
 
Best Western Premiere Ivy Inn & Suites
Cody, Wyoming
Erection of new hotel foundation with 20’ basement walls and concrete parking lot.
 
Private Home
Cody, Wyoming
Erection of multi-dimensional, new home foundation with various wall height and thicknesses. Implemented hollow core flooring for first floor.
​